Confirm that asbestos has been properly abated and control measures are implemented
Rationale: Confirming that all asbestos has either been removed or abated prevents dangerous exposure to asbestos and supports enhanced indoor air quality, contributing to reduced risk of skin irritation, lung cancer, mesothelioma, asbestosis, and other pulmonary diseases.
For the most accurate strategy and documentation requirements, please refer to the digital scorecard made available on the Fitwel Platform.
Requirements
Demonstrate compliance with one of the options below:
Option 1 - Asbestos Control Measures (Full Credit):
To achieve full credit, demonstrate compliance with all of the following requirements:
- Implement asbestos control measures throughout the building(s) that include one of the following:
- abatement
- encapsulation
- enclosure
- repair
- clean up.
- Ensure that the identified control measures are performed by a certified professional.
- Ensure that the identified control measures are required for future renovations within the building(s).
- Ensure that the control measures are implemented in all areas of the building(s).
Option 2 - Asbestos-Free Construction (Full Credit):
The project may achieve credit by demonstrating compliance with all of the following requirements:
- Ensure that the building(s) construction began or will begin after the use of asbestos in construction products was banned in the country or region where building is located.
Compliance Documentation
Design Pathway
Option 1:
- Requirement 1
-
Upload legal documentation (such as a certificate or remediation report submitted to authorities) showing the asbestos control measure that have been or will be implemented within the building(s).
- Checkbox to confirm that the building(s) is in compliance with the asbestos control measures.
-
Checkbox to certify that at least one of the listed asbestos control measures were or will be implemented
-
- Requirement 2
- Checkbox to certify that the identified control measures have been or will be performed by a certified professional
- Requirement 3
- Checkbox to certify that the identified control measures are required for future renovations within the building(s).
- Requirement 4
- Checkbox to certify that the control measures are or will be implemented in all areas of the building(s)
Option 2:
- Text box to input the year construction for the building(s) began
- Text box to input the year in which asbestos was banned in construction products within the local jurisdiction
- Upload legal documentation (such as a certificate or reports submitted to authorities) demonstrating the date that construction on the building began or will begin.
Built Pathway
Option 1:
- Requirement 1
-
Upload legal documentation (such as a certificate or remediation report submitted to authorities) showing the asbestos control measure that have been implemented within the building(s).
- Checkbox to confirm that the building(s) is in compliance with the asbestos control measures.
-
Checkbox to certify that at least one of the listed asbestos control measures were implemented
-
- Requirement 2
- Checkbox to certify that the identified control measures have been performed by a certified professional
- Requirement 3
- Checkbox to certify that the identified control measures are required for future renovations within the building(s).
- Requirement 4
- Checkbox to certify that the control measures are implemented in all areas of the building(s)
Option 2:
- Text box to input the year construction for the building(s) began
- Text box to input the year in which asbestos was banned in construction products within the local jurisdiction
- Upload legal documentation (such as a certificate or reports submitted to authorities) demonstrating the date that construction on the building began