Confirm that asbestos has been properly abated and control measures are implemented
Rationale: Confirming that all asbestos has either been removed or abated prevents dangerous exposure to asbestos and supports enhanced indoor air quality, contributing to reduced risk of skin irritation, lung cancer, mesothelioma, asbestosis, and other pulmonary diseases.
For the most accurate strategy and documentation requirements, please refer to the digital scorecard made available on the Fitwel Platform.
Requirements
Demonstrate compliance with one of the options below:
Option 1 - Asbestos Control Measures (Full Credit):
To achieve full credit, demonstrate compliance with all of the following requirements:
Multi-Tenant Base Building (no on-site management), Multi-Tenant Base Building (with on-site management)
- Implement asbestos control measures that include one of the following:
- abatement
- encapsulation
- enclosure
- repair
- clean up.
- Ensure that the identified control measures are performed by a certified professional.
- Ensure that the identified control measures are required for future renovations within the building.
- Ensure that the control measures are implemented in all areas of the building.
Single-Tenant, Commercial Interior
- Implement asbestos control measures that include one of the following:
- abatement
- encapsulation
- enclosure
- repair
- clean up.
- Ensure that the identified control measures are performed by a certified professional.
- Ensure that the identified control measures are required for future renovations within the building.
- Ensure that the control measures are implemented in all areas of the building.
Option 2 - Asbestos-Free Construction (Full Credit):
Demonstrate compliance with all of the following requirements:
Multi-Tenant Base Building (no on-site management), Multi-Tenant Base Building (with on-site management)
- Ensure that the building construction was completed after the use of asbestos in construction was banned in the country or region where building is located.
Single-Tenant, Commercial Interior
- Ensure that the building construction was completed after the use of asbestos in construction was banned in the country or region where building is located.
Compliance Documentation
Design
Option 1:
- Upload the official report showing the asbestos control measure that was been implemented
- Checkbox to certify that at least one of the following lead control measures will be or has been implemented
- Checkbox to certify that the identified control measures are performed by a certified professional
- Checkbox to certify that the identified control measures are required for future renovations within the building
- Checkbox to certify that the control measures are implemented in all areas of the building
Option 2:
- Text box to input the date the building was constructed
- Text box to input the date in which asbestos was banned within the local jurisdiction
Built
Option 1:
- Upload the official report showing the asbestos control measure that was been implemented
- Checkbox to certify that at least one of the following lead control measures will be or has been implemented
- Checkbox to certify that the identified control measures are performed by a certified professional
- Checkbox to certify that the identified control measures are required for future renovations within the building
- Checkbox to certify that the control measures are implemented in all areas of the building
Option 2:
- Text box to input the date the building was constructed
- Text box to input the date in which asbestos was banned within the local jurisdiction
Comments
0 comments
Article is closed for comments.